LPS Radon Testing and Mitigation Efforts
Air Quality at LPS
LPS manages the air quality in our schools through the heating, fresh air ventilation, and air conditioning systems (HVAC). The HVAC systems manage several factors; for example, air temperature, fresh air volume, and carbon dioxide levels. LPS has completed numerous indoor air quality projects in our older schools and applies best practices in the construction of our new schools. A well-functioning HVAC system mitigates the presence of radon gas in our schools. One element of our fresh air analysis is radon testing. LPS tests a number of schools each year.

Mitigation Steps
If radon testing within schools indicates levels at or in excess of 4 pCi/L, the following mitigation efforts are taken
- Review applicable and current drawings, specifications, photos, and other information regarding the existing building.
- Identify design information for the following:
- Foundations, footings, tunnels, crawl spaces, drainage systems, and utilities.
- HVAC systems, locations, and operational schedules.
- All other relevant building systems, including but not limited to, fire protection, HVAC, electrical service, plumbing, or other potential pollutants.
- Review floor plan diagrams with referenced design information noting suspected or confirmed significant soil, air entry points, or potential locations for such contamination.
- Conduct a visual inspection to help identify any specific building characteristics, hazards, and configurations that may affect the design, installation, and effectiveness of existing systems.
- Take investigative or mitigation actions as necessary to bring facility in accordance with design standards.
- Our team seeks to solve the condition within the building that is allowing radon gas into the building or is not sufficiently ventilating the building to control the radon levels.
School Testing Dates
Here you will find a listing of the year radon testing occurred in each school. In every circumstance of a reading at or above 4.0 pCi/L our team seeks to find the cause and makes necessary modifications. Our team continues with mitigation efforts until retesting confirms the radon levels are below 4.0 pCi/L.
Elementary Schools
School | Latest Test | Proposed Test |
---|---|---|
Adams | November 2024 | |
Arnold | September 2021 | |
Beattie | March 2024 | In Progress |
Belmont | March 2020 | In Progress |
Brownell | September 2021 | |
BSP/Sherill | March 2023 | Winter/Spring 2025 |
Campbell | September 2022 | In Progress |
Calvert | May 2019 | Fall 2025 |
Cavett | October 2024 | |
Clinton | July 2019 | In Progress |
Eastridge | March 2022 | In Progress |
Elliott | January 2024 | |
Everett | October 2024 | |
Fredstrom | September 2022 | Fall 2025 |
Hartley | March 2023 | |
Hill | November 2023 | |
Holmes | October 2023 | |
Humann | December 2022 | |
Huntington | March 2020 | Winter/Spring 2025 |
Kooser | April 2020 | Winter/Spring 2025 |
Kahoa | March 2023 | |
Kloefkorn | December 2020 | Fall 2025 |
Lakeview | October 2024 | |
McPhee | March 2021 | |
Maxey | October 2024 | |
Meadow Lane | March 2021 | |
Morley | September 2022 | |
Norwood Park | October 2023 | |
Pershing | November 2024 | |
Prescott | November 2023 | |
Pyrtle | October 2023 | |
Randolph | November 2023 | |
Riley | September 2021 | |
Robinson | October 2023 | |
Roper | September 2021 | |
Rousseau | September 2022 | |
Saratoga | December 2021 | Fall 2025 |
Sheridan | March 2024 | |
West Lincoln | October 2023 | |
Zeman | March 2021 | |
Wysong | September 2022 |
Middle Schools
School | Latest Test | Proposed Test |
---|---|---|
Culler | March 2022 | Winter/Spring 2025 |
Dawes | March 2024 | |
Goodrich | September 2022 | Winter/Spring 2025 |
Irving | March 2022 | Fall 2025 |
Lefler | September 2021 | In Progress |
Lux | March 2023 | Winter/Spring 2025 |
Mickle | March 2022 | Winter/Spring 2025 |
Moore | September 2022 | |
Nuernberger | March 2023 | Winter/Spring 2025 |
Park | November 2023 | |
Pound | December 2022 | |
Schoo | December 2021 | Winter/Spring 2025 |
Scott | March 2023 |
High Schools & Specialty Programs
School | Latest Test | Proposed Test |
---|---|---|
Lincoln High | March 2023 | Fall 2025 |
East | October 2024 | |
Northeast | March 2023 | Winter/Spring 2025 |
Southeast | October 2020 | Winter/Spring 2025 |
North Star | March 2024 | |
Southwest | January 2024 | |
Northwest | October 2023 | |
Standing Bear | In Progress | |
Hawthorne Facility | March 2024 | |
Yankee Hill | September 2021 | Fall 2025 |
Support Facilities
Location | Latest Test | Proposed Test |
---|---|---|
LPSDO | October 2024 | |
Operations | November 2024 | |
Transportation | April 2020 | In Progress |
Grounds | April 2020 | Winter/Spring 2025 |
Distribution | November 2024 | |
Clifton | November 2024 |